How To: Configuring Project Structures
To use project time tracking in Webdesk EWP efficiently, the appropriate project structures and their bookable projects must be created first.
The following list shows, step by step, the required actions for the new configuration of project time management. Click a link to go directly to the corresponding chapter with extensive descriptions and instructions for the respective organizational element and its functions.
1) Element Types
As a first step, so-called element types must be created in the system. The element type is a kind of definition and describes what type of project it is. In addition, a symbol must be created for each element type. When a new project is added, you must select which element type the project is. Examples of element types are "work package", "main project", "project phase", or "subproject".
As an administrator, you can access the element types via the menu tree under:
MODULES
--> Project Time Tracking
--> Element Types
By clicking "Create element type", new element types can be defined. The following fields must be filled in:
|
Name |
Name of the new element type. Ideally, it should help to divide projects into different classes. |
|---|---|
|
Up to level |
Here you can set up to which (sub)level within the project hierarchy a certain element type can be defined. If, for example, "2" is selected here, a project belonging to this element type can be placed at most 2 hierarchy levels below the top level, e.g., main project (0) --> subproject (1) --> example project (2), but not main project (0) --> subproject (1) --> phase project (2) --> example project (3) |
|
Image set |
Selection of the collection of icons that should be available |
|
Image |
Enter the file path of the image that is to serve as the symbol for the newly created element type |
If you are not sure how to select an image, click the small icon in the lower left corner of the interaction area. A selection of all symbols of the selected image set follows:
- Move the mouse pointer over the desired symbol - with a
right-click and then a click on "Copy image
address", the image address lands in your clipboard.
- Close the image set and copy the image address into the "Image"
field. Delete the entire text up to the last two slashes (e.g.:
"/actions/penguin.png").
- Clicking "Save" saves the new element type including the
symbol.
2) Activities
In this step, the activities should be defined. These are various freely selectable activity descriptions that are assigned to specific projects and can be booked to specify the activity within a project (e.g., administration, installation, planning, documentation). In addition, an activity in the project (e.g., programming) can be restricted to employees of one or more specific Webdesk groups.
As an administrator, you can access the activities via the menu tree under:
MODULES
--> Project Time Tracking
--> Activities
The data table contains an overview of all activities that have already been defined. To add a new activity, click the "Create activity" button. The following fields can be filled in:
|
Short name |
Short name of the new activity, e.g., "MAR" for "Marketing actions" |
|---|---|
|
Name |
Name of the activity that can be booked within a project in the future |
|
Description |
Short description of the activity, closer definition |
|
Valid from |
Date from which the new activity is to be available for booking in the project (usually the current day) |
|
Valid until |
Date until which the new activity is to be available for booking in the project (expiration date) |
Clicking "Save" or "Save and close" saves the newly created activity in the system.
Behavior of Activities
Activities can be added as bookable to project structures (tab "Structures") or to individual projects (tab "Projects"). In addition, an activity can be restricted to individual Webdesk groups via the "Cost Centers" tab.
The final availability of activities in the booking mask of a project follows this logic:
- If not a single activity is assigned to either the project or its associated project structure, ALL activities defined under "Activities" are available for booking in the project.
- If individual activities are added to a project structure, not all activities, but only the activities added to the structure, can be booked for projects within the structure.
- If activities that have not already been added to the project structure are assigned directly to an individual project, they can be booked additionally in this project, but not in other projects of the structure.
| Vergrößern |
The following tabs are available for assigning and restricting activities:
Tab "Structures"
Here the newly created activity can be assigned directly to a project
structure. This activity is then available for booking to all projects contained
in the structure.
Tab "Projects"
Here the newly created activity can also be assigned directly to an
individual, already existing project in which it can then be booked as an
activity.
Tab "Cost Centers"
If a specific group is selected in the list here and added, the
corresponding activity can only be booked within a project by members of this
group(s). If nothing is selected, there are no group-specific restrictions.
3) Project Structures
Every bookable project must be part of a project structure. These structures are mostly organized by the overarching purpose of the projects they contain (e.g., internal projects, customer projects, product development). Within this structure, projects can be organized as main projects or subprojects.
As an administrator, you can access the project structures via the menu tree under:
MODULES
--> Project Time Tracking
--> Structures
The data table contains an overview of all project structures that have already been set up. Clicking the "New structure" button lets you create a new project structure. The following fields must be filled in:
|
Client |
Selection of the client to which the new project structure is to be assigned |
|---|---|
|
Name |
Name of the new project structure, e.g., "Internal", "Customer projects", "Unproductive" |
|
Description |
Short description, e.g., context or purpose of the new project structure |
|
Use all element types |
If this checkbox is activated, all already defined element types are released for projects within the structure |
|
Unproductive |
If this checkbox is activated, all projects within the structure are marked as "unproductive". These properties can be used as filter options in reports as well as in the project time tracking function at the Webdesk kiosk. |
Tab "Elements"
At least one already defined element type must be added to the project structure here. If a new project is now added to the structure, exactly one element type from this list must be selected as the type for the new project. Under the "Up to level" heading you can set up to which (sub)level within the project hierarchy a certain element type can be defined:
Example:
The element type "Main project" is added with the setting "up to level
2" --> this means that a project of the type "Main project" can only be at
level 0, 1, or 2 in the project hierarchy, i.e., at most a sub-subproject, but
not deeper.
Tab "Activities"
Already defined activities can be added to the project structure here.
The activities added to a project structure are available for booking to all
projects within the structure. It is therefore usually more sensible and
time-saving to add activities to entire project structures and not to each
project individually.
Tab "Projects"
The data table contains an overview of all projects that are part of the selected structure. If the structure has just been created, this list is logically empty.
4) Projects
As the most important object and central bookable
medium in project time tracking, projects should of course also
be created. Once project structures and secondary elements such as activities
and element types have been defined, project time tracking can begin immediately
as soon as a project is created.
As an administrator, you can access the projects via the
menu tree under:
MODULES
--> Project Time Tracking
--> Projects
The data table contains an overview of all projects
that have already been created. By clicking the
button, they can be selected and
edited afterwards. Clicking the "New project"
button creates a new project. The following fields can be
filled in:
|
Name |
Full name of the desired new project |
|---|---|
|
Short name |
Desired short name of the project, appears in various overviews |
|
Code |
Project code, e.g., analogous to the work breakdown structure code in project management |
|
Type |
Selection of the element type for the new project; all element types added to the project structure are available for selection |
|
Structure |
Selection of the project structure to which the project is to be assigned |
|
Parent project |
Here a parent project can be selected directly - the new project can thus be defined as a subproject of an existing project |
|
Bookable ... |
Here you select whether time can be booked to this project in principle. |
|
... to all customers |
Here you select whether this project can be booked to all available customers, or only to those predefined in the project |
|
Billable |
Here you select whether the project involves services that are billable to the customer |
|
... default |
If this checkbox is activated, the project is automatically marked as billable. However, this can be deactivated again directly in the booking mask. |
|
Logo |
Option to upload and select a logo for the new project |
|
Planned hours for |
Here the planned time expenditure can be defined, either for this project only or for this project including its subprojects |
|
Description |
Detailed description of the project, its contents, goals, etc. |
Tab "Subprojects"
Here you will find an overview and comparison of the planned and actual
time expenditure for this project including all its subprojects.
Tab "Permissions"
Information and settings on booking and editing permissions for the
project (for more, see
Permission Management)
Tab "Activity"
Already defined activities can be added directly to the new project
here. In the project, all activities can be booked that have been added either
directly to the project or to the associated
project structure.
Tab "Customers"
Previously defined customers (e.g., as clients) can be assigned to the
project here. This makes particular sense for billing or for regular customers
and enables additional information in evaluations.
Tab "Cost Objects"
Here you can specify that time expenditure booked in the project is
assigned to a previously defined cost object, for example a specific product.
The cost object itself can in turn be part of a cost center in Webdesk.
- Static (with % value): fixed (percentage) distribution of time expenditure to selected cost objects
- Dynamic: Automatic determination of the cost object via the assigned home cost center (group) of the booking person
Tab "Attributes"
Here you will find an individually configurable selection of text
fields, which can contain further information about the project and its
properties. The name and number of text fields to be filled in can be defined
in the system parameters (see here). For example, a field "Meeting" can be
defined there. This field is then visible in every project under the "Attributes"
tab and can be filled with free text, e.g., "Project meeting daily at
2:45 PM".
Tab "Kiosk"
This tab is intended for adding one of the Webdesk kiosk devices
(terminal solution for project time tracking) that are currently under
development.
5) Cost Centers
The cost centers shown here are taken directly from the cost centers added as groups in the "Portal & Organization" section and are identical to them. Under MODULES --> Project Time Tracking --> Cost Centers you will only find an overview of all cost centers registered in the system.
6) Cost Objects
Optionally, cost objects (e.g., products) linked to cost centers can also be created and assigned to a specific project. As an administrator, you can reach the overview of all defined cost objects via the menu tree under:
MODULES
--> Project Time Tracking
--> Cost Objects
Use the "Create cost object" button to add a new cost object. The following fields can be filled in:
|
Name |
Name of the new cost object (e.g., "Product B", for development costs) |
|---|---|
|
Foreign key |
Option to enter a reference key in order to transfer time expenditure for cost objects to an ERP system via an interface |
|
Description |
Option for a short description or definition of the new cost object |
|
Cost center |
Assignment of the new cost object to an already existing cost center |
Clicking "Save (and close)" saves the newly created cost object in the system. If you now want to assign a project to this cost object, this works via the menu item "Projects". After selecting a project from the overview, it can be assigned entirely or partially to a cost object in the "Cost Objects" tab.
7) Customers
Another option is to create customers and assign them to specific projects. This makes particular sense for large customers who are involved in several projects. The evaluation and reporting tools of project time tracking can thus also provide information for customer care and support.
As an administrator, you reach the overview of all customers already added via the menu tree under:
MODULES
--> Project Time Tracking
--> Customers
By clicking the "Create customer" button, a new customer can be added. The following fields can be filled in:
|
Client |
Select the client to whose project the customer belongs |
|---|---|
|
Short name |
Abbreviation of the customer name for display in space-limited views |
|
Name |
Name of the customer to be created |
|
Type |
Selection of the customer type: external (outside companies, "classic" customers) or internal (e.g., services for company-internal departments) |
|
Description |
Short description of the customer, important notes, etc. |
Tab "General"
Important contact and address information of the customer can be
entered and saved here.
Tab "Projects"
Here you will find an overview of all projects that are currently
being carried out for / assigned to this customer. Via the
"Add customer to project" button, a new project can be assigned
directly to the selected customer. Alternatively, a previously created customer
can also be added to the respectively selected project in the menu item
"Projects" under the
"Customers" tab.